BETON READYMIK K-250 171,24 M3 x 860.000,00 = 147.266.400,00
TERKIRIM SAAT INI 119,00 M3 x 810.000,00 = 96.390.000,00 RENCANA SAMPAI 100 % COR LANTAI 40,00 M3 x 810.000,00 = 32.400.000,00 PLASTIK COR 11,00 Roll x 65.000,00 = 715.000,00 Total Terambil 129.505.000,00
UD.SALI PASIR PASANG 125.000/M3 ....
ReplyDeleteBETON READYMIK K-250 171,24 M3 x 860.000,00 = 147.266.400,00
ReplyDeleteTERKIRIM SAAT INI 119,00 M3 x 810.000,00 = 96.390.000,00
RENCANA SAMPAI 100 % COR LANTAI 40,00 M3 x 810.000,00 = 32.400.000,00
PLASTIK COR 11,00 Roll x 65.000,00 = 715.000,00
Total Terambil 129.505.000,00
Selisih 147.266.400,00 - 129.505.000,00 = 17.761.400,00
PENGALIHAN BIAYA PEMBELIAN PASIR PASANG 40 M3
Pasir Pasang Tambahan 10 M3*4 UNIT= 40 M3x 125.000,00 = 5.000.000,00
Sisa Biaya ( Beton K-250 ) 17.761.400 - 5.000.000 = 12.761.400,00
Mohon Di Proses Untuk Pekerjaan Plester Bengkel Instrument ..Terima Kasih
pasir pasang
ReplyDelete- code 77 m3
- terkirim 55,48 m3
- permintaan 40 m3 x 125.000
total 95,48 m3
over
DIkirim 22 m3 saja
NO PO : 0097-DKN-IGG.BENGKEL/05.19
*************************************
https://iggbengkel.blogspot.com/2019/05/po-pasir-pasang.html
ReplyDelete